2016-06-13

Pool Project Update


Status

  1.  Pool has been closed since May 20th
  2. Three Leaks in the pool have been located and plugged.
  3. Condensation damage to the walls and ceiling have been repaired.
  4. Water blasting of pool to remove loose paint completed last weekend.
  5. Pool needs to dry for 2 weeks before repainting.
  6. Repainting of the pool should begin in last week of June.
  7. Pool needs to dry for at least 2 weeks prior to refilling.
  8. Gutters being designed.
  9. Installation of gutters (1 to 2 days) should be just before pool is refilled (in approximately 4 weeks).
  10. Target date for reopening – by the week of July 18th 
Outstanding issue
We have not yet been able to diagnose the ceiling leak where you often see a bucket at the front of the pool. This only happens during the winter and has not leaked for months. This implies a condensation issue. We will consult with an expert to determine next steps.