When we
announced the closure of the pool, we estimated a closure of 6 to 8 weeks. We
projected a reopening in the week of July 18. Issues with the pool paint may
negatively affect that date. Details are below.
Pool Paint
You must
have heard the noise in the garden that lasted until 7:45 PM on Tuesday evening.
That noise was from the compressor needed to water-blast the pool a second
time. Although initial water-blasting was completed more than 2 weeks ago, our
contractor has since encountered similar issues as we have had with the same
paint in a pool in another building. Therefore, he is convinced that using this
paint would be a mistake.
Not wanting
to risk a third lengthy shutdown of the pool, we have agreed to use the same
type of paint we have used successfully in the past. This second water-blasting
was to remove the balance of the new paint left over from the first time so
that we can go back to a more conventional solution. Whereas using a new type
of paint that would be guaranteed for 8 years seemed like a good idea at the
time, in practice, it was less than a month before problems began to appear.
It is the
drying time after water-blasting and painting of the pool that causes the long
shutdown so a second water-blasting will cause a delay. However, now that we
have switched to more conventional paint, the necessary wait time for drying
will be reduced. There is no extra cost to us for this change. However, our
contractor is in a legal dispute with the paint supplier.
Gutters
The final
design of the Gutters was approved this week and they are expected to be installed
just before painting starts in the week of July 11th.
Other
There are 2
remaining issues.
As
previously discussed, the problem where we often need to place a bucket at the
front of the pool is still outstanding. The problem is that it has not leaked
for months and is impossible to diagnose.
A new issue
has manifested itself when we did the water-blasting. The concrete pedestal
that supports the hand railing has cracked and needs repair. We are working on
a solution.
Summary
- Pool
has been closed since May 20th
- Three
Leaks in the pool have been located and plugged.
- Condensation
damage to the walls and ceiling has been repaired.
- First
water blasting of pool to remove loose paint was completed June 12th.
- Second
water blasting to remove balance of paint completed June 28th.
- Pool
needs to dry before repainting can begin.
- Repainting
of the pool with conventional paint should begin week of July 11th.
- Paint
needs to dry for 1 to 2 weeks prior to refilling.
- Gutters
ordered.
- Installation
of gutters (1 day) just before painting begins.
- We
require 3 days to refill and heat the pool.
- Target
date for reopening – before August 1st. Despite the lost time
due to the need for a second water-blasting, this is approximately 1 week
late.
No comments:
Post a Comment