Gutters
Two of 3
sets of gutters are installed. The last section should be complete by the end
of the day Monday.
Other Repairs
There are a
few areas that need a bit of epoxy repair. The two small pedestals that secure
the main hand rails need to be demolished and rebuilt.
These
repairs should occur early in the week.
Painting
Painting of
the pool should begin this week. Once the pool paint is dry, we can refill the
pool and go swimming.
We are still
targeting the pool to be operational sometime during the last week of July.
No comments: